Duration

April 2016 to Present

Scope of work

HKE Term Contracts (2 Years) and Refurbishment Projects

Project description

Term Contracts:

  • Field Re-paint and Touch Up Painting Work for Two Years in LPS (2016-2018)
  • Replacement of Fuel Nozzles of Gas Turbine Nos 1-4 & 6 for Two Years in LPS (2016-2018)
  • Thermal Insulation Work in LPS (2016-2018)
  • Stage II and III Boiler Feed Pump Hydraulic Couplings for Two Years in LPS (2017-2019)
  • Overhaul of Electrostatic Precipitator in LPS (2017-2019)
  • C.W. Pumps Overhaul in LPS (2017-2019)

Refurbishment Services

  • Refurbishment of No. 4&5 Coal Ship Unloader (2016)
  • Refurbishment of Stage I Boiler House Roof Ventilation Fans (2017)